Using sitework-related drawings for the SIRTI project, calculate the following quantities:
- Square feet of asphalt paving for the East parking lot, including the driveway to the edge of the street. (1 point)-
- Square feet of asphalt paving for the West parking lot, including the driveway to the edge of the street. (1 point)-
- Linear feet of ½”, ¾”, and 2” pipe connected to Irrigation Control Valve 5, assuming a 2” pipe is used between the valve and the first junction and ¾” pipe is used from the first junction along the main trunk. (1.5 points)-
- Cubic yards of “gravel base course” under the natural stone paving along the north edge of the site, where the bottom of the exterior stairs meets the bike/walking path along the river. (1.5 points)-
Submit any documentation (e.g., marked-up drawings) you used to determine the quantities.