For an organization, the following project schedule is given. Assume that all times are in days.
Task |
Predecessor |
Normal Time |
Crash Time |
Crash Cost Slope |
A |
None |
7 |
7 |
NA |
B |
A |
3 |
3 |
NA |
C |
A |
8 |
4 |
600 |
D |
A |
4 |
4 |
NA |
E |
B |
6 |
5 |
600 |
F |
C, D |
2 |
2 |
NA |
G |
E, F |
6 |
6 |
NA |
H |
F |
5 |
3 |
400 |
I |
G, H |
4 |
4 |
NA |
J |
I |
2 |
2 |
NA |
In a 3- to 4-page Microsoft Word document, address the following: