Benny is the project manager of MNC Project. He has hired an independent contractor for a portion of the project work. The contractor is billing the project $120 per hour, plus materials. This is an example of which one of the following? A.Cost plus fixed fee B.Time-and-materials C.Unit-price D.Lump sum